PROGRESS OF PERMANENT CAMPUS CONSTRUCTION



                                                        Construction of National Institute of
                 Name of the Project                    Pharmaceutical Education and Research
                                                        (NIPER) Campus at Guwahati, Assam



                 Project Value                          159.69 Crore (Phase I)


                                                        M/s. Engineering Projects (India) Limited,

                 Project Management Consultants         New Delhi
                                                        (A Govt. of India Enterprise)



                 Architects                             M/s. Prasad Associates, Hyderabad


                 Contractors                            M/s. NCC Limited, Hyderabad



                 Project Duration                       24 Months from the Date of Issue of LOI



                 Actual Date of Start of Work           20.07.2015



                 Overall Physical Progress in %         73.09% as on 31.03.2020


                 Overall Financial Progress
                                                        112.29 Crores
                 (till March 2020)